- Kiosks and Tanks were marked out on their corresponding plinths for being landed on.
2. Worked with the crane hire company to land the tanks and kiosk, for them then to be bolted to the ground, securing them in place.
3. We then installed the containment for the pipework and cable to be ran from their kiosks to the tanks.
4. The pipework was all dry fitted to ensure a perfect fit then glued ready for pressure testing.
5. The cable was pulled and run from the kiosks to the tanks and probes.
6. Pressure tested the pipework to ensure quality assurance was kept.
7. Electro-fusion welded the pipework acting as containment for any potential chemical leaks.
8. Left ready for the commissioning team.